Название Innovations in copper metallurgy by the example of a realization of a reconstruction project of “Karabashmed” JSC. Part 3. Development experience of a processing technology of slags of autogenous processes
Автор Altushkin I. A., Korol Yu. A., Sizikov A. V.
Информация об авторе

“Russian Copper Company” JSC, Ekaterinburg, Russia:

I. A. Altushkin, Chairman of Board of Directors
Yu. A. Korol, Vice-President, e-mail: u.korol@mail.ru

 

“Aktyubinsk Copper Company”, Aktyubinsk, Republic of Kazakhstan:

A. V. Sizikov, Chief Executive Officer

Реферат

Making the innovation decisions in the processing of autogenous slags was required during the development of “Ausmelt” process, for the effective application of innovative technologies in the main metallurgical process at “Karabashmed” JSC. After the analysis of existing technological schemes and existing limitations on the industrial site of enterprise, there was adopted the decision to use the flotation processing technology of circulating products on metallurgical shop. After the end of construction of processing plant, the enterprise has faced with some difficulties, connected with its driving up to the rated capacity. One of the main failure causes of the achievement of project indicators, was the erroneous forecast of the quantity and composition, intended for the wastes processing, during the development of new autogenous process and adherence of process parameters during the development of flotation concentration process of metallurgical slags. Currently, the company’s specialists worked out the measures for shortcomings elimination.
In the contest of these events, there were carried out the following measures:
– the crushing system was changed with its transfer in two stages;
– the crushing equipment was changed;
– the scheme of materials supplement for crushing and to the silage of finished products was changed;
– the filter equipment was replaced;
– the dosage scheme of flotation reagents was changed;
– the organizational activities were carried out.
The reconstruction of the pulp thickening area and modernization of pumping equipment is planned by the end of 2012. The completed works for the efficiency improvement of processing plant made possible to increase the hourly loading of slag processing from 42 tones per hour to 60 tones per hour, with maintaining of all qualitative indicators of enrichment.

Ключевые слова Innovation, investigation, copper, Ausmelt, improvement, converter slags, furnace slags, processing plant, modernization, productivity
Библиографический список

1. Kokurin D. I., Volkov V. S., Safiullina E. I., Nazin K. N. Innovatsionnaya ekonomika (Innovation economics). Moscow : Ekonomika, 2011.
2. Arustamyan M. A., Zimin A. V. Tekhnologicheskiy reglament na proektirovanie obogatitelnoy fabriki po pererabotke shlakov metallurgicheskogo proizvodstva ZAO “Karabashmed” proizvoditelnostyu 600 tysyach tonn v god (Process procedure on the projecting of the slags processing plant of metallurgical production on “Karabashmed” JSC, with a producti vity by 600 thousand tones per year). Saint Petersburg : “IVS” JSC, 2003.
3. Yadryshnikov A. O., Shenderovich E. M., Efremov I. N., Kuzmin K. B. Tekhniko-ekonomicheskoe obosnovanie stroitelstva uchastka po pererabotke shlakov tekushchego proizvodstva proizvoditelnostyu 600 tysyach tonn po iskhodnomu syryu v sostave ZAO “Karabashmed” (Technical and economic substantiation of an area construction for the current production slags processing, with 600 thousands tones productivity of the starting raw materials on “Karabashmed” JSC). Saint Petersburg : Mekhanobr Engineering, 2005.
4. Semidalov S. Yu. Tekhnicheskoe perevooruzhenie uchastka po pererabotke shlakov tekushchego proizvodstva. Opredelenie tekhnicheskoy vozmozhnosti pererabotki na ZAO “Karabashmed” 600 tysyach tonn v god shlaka pechi Ausmelt i konverterov s massovoy doley medi ne menee 3,5 % (Technical re-equipment of an area of slags processing of the current production. Definition of the technical possibility of processing of 600 thousand tones of slags per year of Ausmelt furnace and converters with copper total mass fraction by not less than 3,5 % on “Karabashmed” JSC). Ekaterinburg : Finpromko-Unipromed, 2011.
5. Razumov K. A., Perov V. A. Proektirovanie obogatitelnykh fabrik (Projecting of processing plants). Moscow : Nedra, 1982.
6. Mitrofanov S. I., Barskiy L. A., Samygin V. D. Issledovanie poleznykh iskopaemykh na obogatimost (Researching of mineral resources on the beneficiation ability). Moscow : Nedra, 1974.
7. Spravochnik po obogashcheniyu rud. Tom 1 (Reference book on the ore be neficiating. Volume 1). Moscow : Nedra, 1972.
8. Spravochnik po obogashcheniyu rud. Tom 2, chast 2 (Reference book on the ore beneficiating. Volume 2, part 2). Moscow : Nedra, 1974.

Language of full-text русский
Полный текст статьи Получить
Назад